Three Pilots, One National Standard: A 36-Month Roadmap for Indonesia’s Multi-Hazard Response Capability

Author

JINJIA

Date

2026-08-28

Three Indonesian disaster-response pilot regions connected by one national SAE interoperability standard

Share

The fastest way to weaken a promising national program is to scale it before it has been tested in the country’s hardest operating conditions. The second-fastest way is to run a technology demonstration that proves individual equipment works but says nothing about multi-agency command, lifecycle readiness or integration with existing national systems.

Indonesia needs a different path: a jointly governed reference architecture, three operationally distinct pilots, transparent baseline KPIs and a scale decision based on evidence.This approach matches BNPB’s 2025-2029 direction. The Strategic Plan emphasizes collaboration from national to regional levels, integrated early warning and emergency handling, community resilience, logistics and equipment, Pusdalops capacity and stronger interoperability. The program described here is not a parallel national platform. It is a method for validating the field execution layer beneath those priorities.

  1. Indonesian ownership. BNPB governs the reference architecture, national interfaces, validation framework and scale decision.
  2. Protect systems of record. BNPB, BMKG, InaRISK, DIBI and Pusdalops data remain authoritative; SAE consumes and returns only approved operational information.
  3. Mission-based packages. Procure a verified response capability – people, platforms, modules, communications, training, spares and maintenance – rather than unrelated line items.
  4. Open interoperability. Approved existing radios, sensors, UAVs, UGVs and vehicles should connect through documented interfaces wherever technically and legally feasible.
  5. Baseline before target. Measure the current process before setting improvement thresholds.

Local capability transfer. Indonesian partners must be able to integrate, train, maintain, support and progressively localize the system.

Reference mission. Validate warning-to-tasking, dense urban access, flood evacuation, field energy, multi-agency common operating picture and robotic support in industrial or hazardous fire.

Potential participants. BNPB/BPBD and Pusdalops, relevant fire and rescue service, Basarnas, BMKG, health and public-works functions, infrastructure operators and other authorities selected by the government.

Capability mix. SAE field node; approved communications; amphibious 8×8 or other flood-access platform where appropriate; F120 high-mobility truck; fire-rescue UTV and compact mobility; pumps, lighting, energy, medical/cold-chain and evacuation modules; firefighting robot or UGV for a controlled hazardous-zone scenario.

What the pilot should prove. Can an authoritative warning become a named task? Can teams share route, shelter, water, hazard and asset status? Can the field cell continue during a power or connectivity interruption? Can robotic data be integrated into incident command rather than viewed on a separate screen?

Reference mission. Validate detection-to-ground confirmation, soft-terrain access, water establishment, multi-shift sustainment, responder accountability and monitoring through operational closure.

Potential participants. BNPB/BPBD and Pusdalops, Ministry of Forestry/Manggala Agni, BMKG, local fire and emergency services, TNI/Polri support, community fire groups and other locally authorized partners.

Capability mix. SAE edge node and mesh; BN117 or equivalent tracked/low-ground-pressure carrier; UTV and compact mobility; Delta 150 or tracked carrier for payload and reconnaissance; pumps, hose, flexible storage, field energy, lighting, UAV/thermal inputs and sustainment modules.What the pilot should prove. Can the operation maintain one picture of teams, pumps, water points, hose routes, thermal observations, hazards and tasks? Can the package move beyond the roadhead without exhausting the crew? Can maintenance and resupply support more than one shift? Is the after-action record complete enough to improve the next deployment?

Reference mission. Establish a local command, communications, reconnaissance, power, medical, water and logistics cell after an earthquake, tsunami, volcanic eruption or landslide has disrupted infrastructure.

Location principle. The theatre should be selected by BNPB using risk, access, institutional readiness and exercise feasibility. The concept is relevant to Nusa Tenggara, Sulawesi, Maluku and Papua, but the pilot site should not be predetermined by a supplier.

Potential participants. BNPB/BPBD and Pusdalops, Basarnas, BMKG and technical monitoring agencies, health and public works, local government, TNI/Polri support, telecommunications and utility partners, and community organizations.

Capability mix. Deployable SAE edge node; mesh, satellite and approved radio options; F120 or other high-mobility logistics platform; 8×8 amphibious capability where water access requires it; compact mobility and UGV reconnaissance; mobile energy, lighting, water, medical/cold-chain, shelter and logistics modules.

What the pilot should prove. How quickly can a local common picture be established? Which critical loads can be sustained? Can route, bridge, shelter, casualty, supply and team status remain available when external infrastructure is interrupted? Can national reinforcement see and join the local operating model when it arrives?

KPI familyExample measuresWhy it matters
TimeWarning-to-tasking; field-network activation; first field confirmation; first critical capability on sceneMeasures the complete response chain, not vehicle speed alone
ReachTime and payload delivered beyond roadhead; flooded/soft-terrain sectors accessed; route status updatedShows whether the system closes physical access gaps
SafetyPersonnel accountability; SOS/evacuation handling; remote red-zone tasks; exposure and near-miss reportingTests whether technology reduces risk in operational practice
CoordinationTask acknowledgement/completion; cross-agency handover; common-picture availability; incident-log completenessDemonstrates shared execution, not parallel screens
ReadinessEquipment availability; training qualification; spares; maintenance turnaround; multi-shift enduranceProtects lifecycle value after the demonstration
InteroperabilityApproved systems connected; data exchange success; offline/online synchronization; user acceptancePrevents a new information silo

The scorecard should contain a small set of agreed definitions. For example, “field network active” must mean more than a device being powered on; it should require that a defined group of users can see and acknowledge the incident. “Responder accountability” must specify who is included and how stale position data is treated. Clear definitions make pilot results comparable.

PhaseTimeCore outputsDecision gate
Co-design and baseline0-90 daysGovernance charter, scenarios, system-of-record map, interface priorities, safety case and baseline KPI definitionsApprove pilot scope and authority
Integration and field pilot3-9 monthsLocalized SAE workflows, configured platform/module packages, training, tabletop, controlled exercise and initial field validationConfirm technical and operational readiness
Multi-region validation9-18 monthsTwo additional pilots, seasonal testing, multi-shift sustainment, interoperability evidence and revised doctrineDecide standard packages and gaps
National framework18-36 monthsReference architecture, procurement/acceptance framework, Pusdalops integration pattern, training and maintenance network, continuous-improvement cycleAuthorize scaled regional adoption

Governance and doctrine

Define authority, information access, task ownership, offline decision rights, interagency handover and after-action responsibility. Technology must follow Indonesian command practice.

Data and integration

Map authoritative sources, minimum operational data, API priorities, cybersecurity, hosting, retention and synchronization. Begin with the smallest dataset required to support a real workflow.

Platforms and mission modules

Select terrain-matched carriers and modules. Standardize interfaces, mounting, power, safety, communications and acceptance tests so that capability can evolve without replacing the whole fleet.

People and exercises

Use role-based training for commanders, operators, maintainers and field teams. Require a tabletop, controlled field exercise and after-action review for each pilot stage.

Lifecycle readiness

Define spares, preventive maintenance, battery/fuel plans, software support, calibration, storage, inspection and service-level responsibilities before the pilot begins.

Evidence and scale

Instrument the workflow, compare against baseline, record limitations and publish an Indonesia-owned validation report. Scale what is proven; redesign what is not.

StakeholderProposed role in the program
BNPBSponsor the reference architecture, national governance, system-of-record interfaces, pilot selection and scale decision
BPBD/PusdalopsOwn local workflows, operate pilots, validate usability and maintain regional readiness
BMKG and technical agenciesProvide authoritative warnings and approved technical data; validate downstream dissemination
BasarnasValidate search, rescue, evacuation and first-response workflows within its mandate
Ministry of Forestry/Manggala AgniValidate karhutla doctrine, ground operations and forestry-fire requirements
Fire and rescue servicesValidate urban, industrial and local fire-rescue workflows
TNI/Polri and other supporting institutionsParticipate according to Indonesian authority, incident structure and support requirements
Indonesian industry and academiaLocal integration, cybersecurity, training, maintenance, localization and independent evaluation
Jinjia Special EquipmentSAE, mobility platforms, mission integration, documented interfaces, training and capability transfer

A national tender or framework should describe capability packages and acceptance outcomes. A flood response package, for example, should specify access class, payload, evacuation function, field power, communications, SAE integration, operator training, spares, maintenance, exercise and KPI acceptance. This makes lifecycle cost and operational value visible.The same logic protects Indonesia from both extremes: a closed proprietary system that cannot integrate, and a collection of open components that has never been engineered or exercised as one response capability.

ADEXCO describes itself as a pentahelix platform connecting government, industry, innovators and disaster-management stakeholders. That makes the 9-12 September 2026 event more than an equipment exhibition. It is an opportunity to convene the institutions that must jointly govern a national field architecture.

The proposed first outcome is simple: a BNPB-led technical working session, followed by one tabletop and field demonstration, then one reference pilot with agreed baseline KPIs. The program can grow only after Indonesian operators have produced the evidence.

Three pilots will not solve every national challenge. They can do something more valuable at the beginning: establish a common language for warnings, tasks, access, safety, readiness and interoperability. That is the foundation on which a national system can scale.

Any Terrain. Any Mission. One System. Powered by SAE.